Marshall
Highlights for 1962
(Source Note: The following information is presented
here as published in a news release issued in late 1962 by
the Marshall Center Public Affairs Office.)
HUNTSVILLE, Ala. - - The NASA Marshall Space Flight
Center, while building for the future on the ground, had a
banner year in space during 1962.
Eight MSFC space vehicles were launched, including two perfect
Saturn tests.
On Jan. 26 an Atlas Agena-B lifted a Ranger 3 payload and
April 23, another Atlas Agena-B combine lifted Ranger 4 which
hit the moon. The second Saturn made a perfect flight April
25. A Centaur was launched May 8 but failed 5; seconds after
liftoff.
The Mariner I Venus probe was launched July 22 on the Atlas
Agena-B, but it was destroyed by the range safety officer
290 seconds after liftoff. The now-famous Mariner 2 spacecraft
which passed Venus was sent aloft by the same rocket system
August 27. Ranger 5, launched Oct. l8. missed the moon and
went into orbit around the sun.
Another Saturn was successfully launched Nov. 16. Meanwhile,
back on earth during 1962, several contracts were awarded
for facilities at the Michoud Operations in New Orleans. It
was chosen by MSFC as a site for manufacture and assembly
of Saturn boosters.
A management team of about 60 MSFC personnel moved to the
new facility to begin preparing the plant for operation, scheduled
to start in the summer of 1963.
Preliminary engineering work for establishment of a centralized
site for static testing of the Saturn S-1 and S-IC stages
to be produced at Michoud was going forward at the 13,500
acre Mississippi Test Facility nearby. This work was about
40 percent complete as of June 30.
Easements were being secured for a buffer zone of 128,400
acres.
Progress was recorded on construction of the new static
test facility at MSFC, designed for test firing of the Saturn
C-5 booster. Foundation work was nearing completion. The facility
was scheduled for use by January, 196l. Astrionics, Quality,
Manufacturing Engineering, Propulsion and Vehicle Engineering
Divisions, and other organizations added new facilities .
Work on the new $4 million Central Laboratory and Office
building at MSFC was expected to be nearly completed in January.
It is a nine story structure located on Rideout Road. A six
story Engineering and Administrative building is to be erected
adjacent to the Central Laboratory and Office facility. Preliminary
drawings for the $2, 500,000 building have been completed
by an architectural engineer.
Last January, Dr. Wernher von Braun, MSFC director, and Dr.
E. F. M. Rees, deputy director for Research and Development,
were named to the Management Council of the Office of Manned
Space Flight by D. Brainerd Holmes, OMSF director. The Council
was organized to speed development of spacecraft, boosters,
and support equipment necessary for the success of the manned
space flight programs.
MSFC's Launch Operations Directorate was dissolved during
this period and Launch Operations Center, a new field installation
of NASA, was established. The Launch Vehicle Operations Division
was created at Huntsville and assigned responsibility for
MSFC Launch Operations at LOC.
Another administrative revision was establishment in February
of the MSFC Central Planning Office, with the mission of assisting
the Director's office in planning, program coordination, and
reporting activities. Consolidated in Central Planning Office
were the Operations Analysis, Technical Program Coordination,
and Lunar Program Planning Office.
Concurrent with the establishment of the Central Planning
Office, the Technical Services Office was abolished and two
new offices were created: the Facilities Engineering Office
and the Support Services Office.
In June, legal activities of MSFC were consolidated in the
Chief Counsel's office. The office of Patent Counsel was discontinued
and the office of Associate Chief Counsel for Patent Matters
was established.
A total of 80 boards, committees, and working groups administered
MSFC's varied programs during the period.
An important event occurring during February was MSFC's
receipt of an Award of Honor from the National Safety Council
for having logged nearly four million working hours without
a disabling injury or fatality.
An H- 1 rocket engine was fired in February for the third
time after being dunked four hours in salt water at Cape Canaveral.
The test was a phase of an engine recovery program to determine
the effects of salt water on components. A cluster of eight
H-1 engines make up the Saturn booster.
A contract for $8,910,962 was signed in March with the Boeing
Company of Seattle calling for early work on first stage development
of the advanced Saturn launch vehicle. Other funds have been
added to this contract during intervening months. Ultimately
the contract will be worth more than $300 million.
In April, a pre-proposal conference was held at the Marshall
Center after NASA issued a request for proposals from industry
for a detailed systems definition and preliminary design of
the Nova launch vehicle.
MSFC, in the spring, issued nine major study awards on future
efforts. They included such studies as "Early Manned
Planetary Missions" and "Advanced Lunar Transportation
System."
Also in May, the Lockheed Missiles and Space Co., of Sunnyvale,
Calif., was selected by NASA for negotiation of a contract
for the design, development, fabrication and test of the Reactor
In Flight Test (RIFT) vehicle, It is estimated that the total
cost of the RIFT stage development will be about $180 million.
A major Saturn award was made during August to the Chrysler
Corp. Space Division in New Orleans to produce 21 Saturn C-l
boosters for $215, 502, 744. Chrysler had begun work under
an interim contract signed in February.
The same month NASA signed an award with Douglas Aircraft
Company for the design, development, fabrication and test
of the Saturn S-IVB launch vehicle stage. Estimated cost of
the contract, extending through 1966, is $141,100,000.
President John F. Kennedy and key members of government
visited Marshall Center Sept. 11 for a first hand look at
the space effort.
During October, NASA, announced completion of preliminary
plans for the development of the Mississippi Test Facility
which will be built to test the huge rocket stages and engines
required to launch Apollo lunar missions. It is located 35
miles from the Michoud large rocket manufacturing complex
where final assembly of the rocket stages will take place.
William C. Fortune was named manager of the NASA Marshall
Center Mississippi Test Facility.
In other action NASA assigned project management of the
liquid hydrogen fueled Centaur launch vehicle to NASA's Lewis
Research Center during October, along with management responsibility
for the M-l hydrogen engine.
NASA's Saturn S-IV rocket stage was fired during October
for a full flight duration test of all six engines. This propulsion
test vehicle ran seven minutes at the Douglas Aircraft Sacramento,
Calif., test facility. Another S-IV stage was transferred
to MSFC and mated with other C-1 components at the dynamic
test stand.
NASA's J-2 engine, which will power upper stages of Saturn
space vehicles was also given its first long duration test
during October at Rocketdyne's Santa Susana facility in California.
Marshall Center employees shattered United Givers Fund donation
records in November by giving nearly $100,000 to the Huntsville-Madison
County UGF.
Twelve astronauts, including nine who were recently selected,
visited the Marshall Center at the end of November to get
acquainted with MSFC and its space vehicle development work.
D. Brainerd Holmes. director of the Office of Manned Space
Flight, and several members of his staff joined in the talks
with Dr. von Braun and members of his staff.
NASA announced Dec. 12 that MSFC's Agena program would be
transferred to the Lewis Center to allow Marshall to concentrate
all of its efforts on the vital Saturn vehicle development
for the manned lunar landing program.
Back to top |