Marshall
Highlights for 1974
The appointment of a new director, a major reorganization
and associated personnel reductions, the end of the Skylab
mission and further development of a variety of programs
highlighted 1974 at the Marshall Center.
Dr. William R. Lucas was named in March to succeed Dr.
Rocco A. Petrone as director of the Marshall Center. Dr.
Petrone accepted the post of associate administrator at
NASA Headquarters in Washington, D.C.
Dr. Lucas, who has been in the science and management
areas at MSFC and its predecessor organizations for 22 years,
assumed his duties in June after serving as deputy director
for four years.
Richard Smith was named deputy director in November.
The major reorganization and streamlining of the center
became effective May 30.
The total number of permanent civil service personnel
at the Marshall Center dropped from 4,980 in January to
4,357 as of Dec. 14. The number of support contractor personnel
also declined, with 2,297 at the beginning of 1974 and 1,904
as of Dec. 14.
The total direct payroll for the Marshall Center was $106,144,265.47
for calendar year l974.
The record-breaking Skylab mission, composed largely of
Marshall-developed hardware, came to a close Feb. 8 with
the splashdown of the Skylab 4 astronauts.
Dr. James C. Fletcher, NASA Administrator, visited the
Marshall Center twice in 1974 once in April and in November,
each time to present special Skylab awards.
Development of major programs of the future continued
to go forward during 1974, with the next flight mission
scheduled being the Apollo Soyuz Test Project (ASTP) in
July, 1975.
U.S. and Soviet spokesmen report that all aspects of the
ASTP are on schedule. Joint crew training was conducted in
the U.S.S.R. June 23-July 15 and in the United States Sept.
9-30.
The launch vehicle for the Apollo, Saturn IB-210, was
removed from storage at the Vehicle Assembly Building, Kennedy
Space Center, in September for the beginning of post-storage
checkout.
Soyuz 16, the Soviet ASTP forerunner, completed a successful
mission before the end of the year with a safe landing on
Dec. 8.
A Space Shuttle Main Engine component was first hot fired
on April 14 at Santa Susana, Calif., in a successful run
of a preburner assembly.
Shuttle model acoustic tests were underway by the first
of September at the Marshall Center. Also in September,
$6.1 million was earmarked for Shuttle facilities at the
Marshall Center.
A contract was awarded in November to Algernon-Blair Industrial
Contractors Inc., of Atlanta for the modification of the S-IC
test stand at the Marshall Center for the structural testing
of the Shuttle's External Tank.
A contract for the construction of the Spacelab, being
developed by European countries, was awarded by the European
Space Research Organization to ERNO-VFW-Fokker on June 5.
In May the Marshall Center issued requests for proposal
on six studies related to the Space Tug, a reusable stage
to be carried in the Shuttle, and in July the contracts
for these six studies were issued.
The Marshall Center began a project in January aimed at
developing solar energy technology. MSFC was named in September
the lead NASA Center for carrying out the agency's responsibilities
under the Solar Heating and Cooling Act of 1974.
Test operation was begun as construction was completed
in early June on a house using only solar energy for its
heating and cooling needs. By early December, the house
was collecting enough solar energy to fulfill its heating
requirements, with air conditioning capability having also
been demonstrated earlier in the year.
|